Operators of the contractor these days finalizing the construction of the pedestrian footbridge over the channel of the Rambla de Benipila connect the street with Doctor Luis Calandre Health Center Bario de la Concepción.
This is one of the projects included in Plan E and for which the City has requested an extension for completion because of its technical complexity.
The bridge structure is made of metal and being welded section by section along the Rambla.
Will have a light 36 meters and a width of 6.4 meters.
It is estimated that weigh 40 tons and will need a few days using a special crane for placement between the two margins of the wadi.
Its budget is EUR 1,355,066.
One of the most striking aspects of the gateway will be the pink gum which is painting.
It will be recalled conversion Neighborhood Health Center of Concepcion as the head of the west side of town and the allocation of patients in the area near the Alameda, necessitate the construction of this walkway will be completed with ramps gently sloping access.
Source: Ayuntamiento de Cartagena