This morning the Mayor, Pilar Barreiro, has held a series of visits with the residents of The Plan, The Albujón and The Aljorra.
The purpose of these visits was to monitor the process works and having contact with neighbors of each of these areas of municipio.Estos three projects completed in the first half of 2010 as it was established.
First, the mayor has visited the work of the Social Local Plan.
Pilar Barreiro explained that this is an old aspiration of the inhabitants of this area.
Since even today have been occupying a room with too many shortcomings.
The new clubhouse is 80 square meters and will allow it to carry out their activities with dignity.
A new initiative, the Mayor added that this is a local social model that is beginning to implement now, and that is a constructive system faster and cheaper.
In addition to the work of local social, also conditioned to leaving a children's playground for the children of the Plan.
Also construct a sidewalk and a housing attached to this venue.
POOL IN THE Aljorra
On the other hand, have visited the La Aljorra.
This is a municipal swimming pool that is running near 90%, in the absence of some internal details to completion.
Barreiro has reported that The Aljorra suffered complications and had to seek a postponement of the play, but completed within the period established in the extension.
The work of the Aljorra be followed by a second phase with the E Plan, which provides for the provision of additional sports equipment, specifically a paddle and also the adequacy of the environment.
E Investment Plan will be 1,696,184 euros.
These works, which began in spring 2009, including a glass of 25 by 8.5 meters, a spa area for both sexes and a fitness center with separate locker rooms.
The coverage has been used a fixed set of laminated wood arches.
It has been searched to encourage solar use exit to the outside during the summer with a place of connection from which you can control access and distribution of all sports venues and exhibits or to support themselves and from being accecible.
SPORTS IN THE Albujón
Next, the Mayor has visited the new facilities Polideportivo El Albujón, which also are nearly completed.
The status of this work is well advanced, has made 85% of its execution.
Soil are being finalized, the costumes and some hits.
This flag was begun in March 2009 and is part of the Second Investment in Sports Facilities Plan funded by the City and the Autonomous The contract is 1,291,610.68.
For which the City has made the field and 60% of the budget.
As for the characteristics of the facilities, it is a indoor sports court sports such as soccer, handball and basketball, including how new gym, locker rooms and two buses and two singles.
Furthermore, in the top tiers of the building will accommodate 230 people and seating for the disabled on the tarmac.
Source: Ayuntamiento de Cartagena