The actions focus on the rehabilitation of sleepers and rails for a length of 1,800 m, allowing access to the dock Prince Felipe
The work is performed by a "pairwise method" of placing pre-assembled sections of track in its entirety
The government delegate in Murcia, Rafael González Tovar, Adif reportedly has invested more than € 330,000 on improving and modernizing the road infrastructure in the terminal of tailings.
This action, which is in progress with completion scheduled for mid next September, will get increased reliability of rail facilities, resulting in improved performance and greater facilitation of rail traffic.
González Tovar noted that with this investment, which comes under the chapter on Special Fund for the Revitalization of the Economy and Employment, will be achieved to increase the quality and performance of the railway facilities Escombreras terminal.
In particular, investment has been earmarked for improvement works in 1,800 m of the general route of the freight terminal, from which it provides access to the dock Prince Felipe.
To undertake the improvement of railway track, proceed through the "method in pairs, ie the placement of sections of track with a length of about 18 m that have been previously mounted in its entirety, both rails and sleepers.
This method speeds up the full replacement of elements of the road.
The Government delegate noted that the works are part of the improvement program is underway Adif at stations, installations and equipment of its ownership of the conventional network.
Source: ADIF