Cartagena City Council has opened the bidding deadline of the local social construction of the new Vista Alegre included in the Investment Plan and Provincial Districts 2008-2009, a period which will run until September día17.
With a budget of basic tender amounting to a total of 250,000 euros, the construction of the new clubhouse has a lead time of eleven months, as published in the Official Gazette of the Region of Murcia.
All documentation and information regarding available at the website of the Municipality: www.cartagena.es.
On-line services.
Contractor Profile.
Applicants must submit the documentation required in the Contract Management Unit of the City of Cartagena.
IMPROVEMENT DISTRICTS
The Neighborhood Plan and Provincial for the period 2008-2009 includes a total of 66 works with a budget of 7.8 million euros (7,853,604 euros) provided by the Autonomous Community and the City, at a rate of 90 percent the first and 10 percent in the second.
Most of the budget goes to work for the renovation of streets, including firm, sidewalks, pavement and lighting, amounting to 370,000 euros in 26 projects.
The plan includes fifteen projects for the renovation of public lighting systems for an amount of 1.4 million euros and 600,000 euros for asphalting of roads and town streets.
Moreover, the neighborhood plan foresees an investment of 1,220,000 euros for the renovation and creation of local neighborhood, as the local office of Vista Alegre, which now occupies us, or the School of Music Marfagones Mills.
The biennial model based on the Plan allowed to undertake major works without having to divide it into phases, which gives flexibility to put the infrastructure as quickly as possible available to the neighbors.
Source: Ayuntamiento de Cartagena