The government of Spain starts the conditioning of the Rambla del Portus, from Cartagena in the hamlet of Galifa (07/05/2009)

Fuentes Zorita sign the contract works, whose budget exceeds € 315,000 award

This project will employ 23 people and will benefit a population of about 210,000 inhabitants

The president of the Hydrographic Confederation of Segura (CHS), José Salvador Fuentes Zorita, has signed a contract for the refurbishment of the Rambla del Portus in the hamlet of Galifa Cartagena, whose budget amounts to EUR 317,994.92 and the term implementation is 5 months.

The winning company is SA Building and Studies (Cyes, SA), which will begin in a few days work.

This project, part of the Special State Fund for Promoting the Economy and Employment, will solve the problems caused in the stretch of road E-21, which connects the districts of Quarries and Galifa Cartagena, when rain falls of some importance , causing traffic courts by flooding of the road.

Therefore, this area of Cartagena need an efficient disposal of stormwater through the downstream gully, preventing rain water flooding.

In this sense, the CHS, within their functions in terms of packaging channels, aims to solve the problem, with the recess in the flush of Rambla upstream and the placement of a series of concrete pipe under the road while conducting walls made of concrete and stone breakwater to protect the margins of the wadi.

The wall of the left side of the promenade also serves as protection of the road that goes from the road to a housing stock, whose output is placed signs.

This road will be paved with triple surface treatment, asphalt emulsion ECR-2.

In addition, the CHS proceed to the clearing and cleaning of the land plus demolition of the masonry brickwork or clearing the land.

In addition, the CHS perform a embankment, slope profile, the surface rasanteo coronation and preparation of the seating surface of the road, and a breakwater attached to protection channels.

Other work includes the action is the implementation of a concrete wall on both sides

Source: MARM

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información