More than half of the draft Plan E are already in progress (26/03/2009)

The Councillor for Infrastructure, José Vicente Albaladejo, took stock of the current status of the recruitment process works and projects included in Plan E to be funded from the Local Investment Fund, 63 performances in total of which 48 are already awarded and under contract, of which 33 have approved the minutes of setting out, phase just before the start of the execution of works.

Thus, only 15 projects would be awarded.

These statements were undertaken during the presentation Albaladejo third set of actions the State Plan, a series of works to be carried out in urban area (pedestrian belt The turnstile, renovation of the plaza López Pinto) and the expansion of the city (North Access Lighting, urbanization of the street Juan Fernandez), of which the municipal officers are already preparing reports for adjudication.

The council has stressed that in the modern part of town, which is what is known as the Eixample, the works will be in line with what is being done on the street Angel Bruna and what was done in Jorge Juan, uniting aesthetics also continue in another project, this non-Plan E, as is the continuation of Angel Bruna.

THE REEL AND LOPEZ PINTO

The works in this area will focus on the approaches to the windlass (a pedestrian belt has a budget of 1,750,000 euros) and the renovation of the Plaza de López Pinto (1,103,482 euros), with an expected lead time six months.

In the first case, the pavement will be used Cabezo stone, paving stone, white stone strip Turkish albero.

The furniture consists of aluminum wall paper type, woodland composed of 40 units and pedestrian lights (45 units) and recessed into the ground (82 units).

In López Pinto, paving materials also used the same black basalt stone and edging bubbles.

ESTATE OF JUAN FERNANDEZ

The project involves the renovation of the drinking water supply, paved areas for pedestrians and road traffic, renovation, installation of public lighting, surface drainage network and gardening.

For exclusive use of pedestrians will be an area of 10,430 meters square, 3,350 for use of vehicles and 2,216 meters for parking.

Be used for paving polished terrazzo tile, concrete paving and asphalt mix.

As the lights, road lights to be placed 96 and 94 for pedestrians, and to include gardening and Jacaranda mimosifolia negundo.

The budget of 2,334,574 euros and the execution time of 8 months.

NEW PAVEMENT TO GARDEN CITY AND AVENUE OF MURCIA

With a budget of 650,698 euros in the first case and EUR 1,681,158 in the second, will be a renewal of water infrastructure in the area and replacement of the affected services, for which is expected within six months implementation.

It has also been carried out to strengthen the firm in Avenida Reina Victoria, amounting to 250,313 euros, completing the renovation of paving in the area of the Eixample.

NORTH LIGHT ACCESS

The works will include the placement of 136 luminaries of four types, distributed in two rows, one on each side of the road, from the Severo Ochoa Square to the roundabout at The Tejeras.

The solution adopted consists in the construction of a median separator and a half feet wide to accommodate the streetlights.

Among the Liberty Plaza roundabout and the Greenway to be built in the path of the old Chinchilla FC Cartagena ", includes the service road on the right bank and the road of Via Verde of the right bank to provide access to the City of Justice and other municipal activities in the area.

The project budget is EUR 1,985,023 and the contract period of six months.

NEW ACCESS TO HEALTH CENTER OF THE DESIGN DISTRICT

They are building a pedestrian bridge that allows reaching the health center across the Rambla, which will be 36 m long and 6.4 meters wide.

The bridge, which has a budget of 1,355,066 euros and employ 12 workers, will start from the street Dr. Luis Calandre and will be the fourth connection on the Rambla de Benipila, and a new entrance to the neighborhood.

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información