The works of Murcia Door pedestrian continue the pace of work expected, and despite the start of the second phase - the area between Plaza Castellini and Icue - will be postponed until after Easter, work has continued Street Administration.
Thus, during these days has made the replacement and improvement works of sanitation and once completed, is being carried out the installation of paving stones and slabs in the driveway of the road.
As you may recall, last week opened to the public Gate area of Murcia, which has been released and looks pavement and new street furniture.
In total, pedestrian works will affect a total of eight blocks, covering an area of 9,500 square meters.