The second phase of the remodeling market Santa Florentina will start after Christmas.
The postponement was requested by the market traders themselves, to avoid qie works interfere with the sales campaign during the holidays.
This has been one of the main agreements has been reached in the meeting held last week by the councilman of Youth, Tourism and Trade, Javier Herrero with traders in the wake of the start of construction scheduled for late November.
As reported by Javier Herrero, during the meeting identified the priorities to be undertaken in this phase, which will begin running on January 12, such as repairing the roof and the convenience of the woodwork finish higher.
The cost of the second phase of the renovation of Santa Florentina market amounted to 200,000 euros, works that, once started, will last between four and six months.
In addition to the waterproofing of roofs, will be carried out changing the lighting, cleaning and carpentry truss exterior windows and doors, as well as inspection of the structure of the basement in the face to provide for the next phase, so as to certify that they needed the demolition of the floor, as happened in the first phase, affecting fish stalls.
Source: Ayuntamiento de Cartagena