Work on the first phase of construction of the Health Center of San Anton in Cartagena will conclude this summer (07/02/2016)

The Ministry of Health will resume in the coming days the works of the Health Center of San Anton in Cartagena, belonging to the Health Area II, in order to complete the work planned in the first phase, unemployed after the resignation of the contractor.

Through Murciano Health Service (SMS), the Ministry of Health has awarded the first phase of the construction of the center, which began in early 2015.

The works were stopped by the inability of the company awarded the initial competition to continue with the work, after which the SMS has developed the need to award again and resume work as soon as possible procedure.

So far it has executed 30 percent of the work.

By awarding the new record, amounting to 414,952 euros, it will have to be completed in summer 2016.

The first phase of the construction affects an area of ​​518.09 square meters, spread over a plant that will house the query area of ​​Pediatrics, Administrative Area and Support Services.

Second phase valued at 3.1 million

The second phase of construction of the new health center of St. Anton, valued at 3.1 million euros, will cover an implementation period of 16 months and will encompass the remaining units of this infrastructure.

The new health center of St. Anton is a priority to remedy the weaknesses of the existing building because they are 30 years old and his inability to growth.

Source: CARM

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información