The mayor requested an audit of the Palacio de Deportes (23/06/2015)

Jose Lopez and Ana Belen Castejon, Mayor and Deputy Mayor of Cartagena respectively have first visited the Sports Palace for the actual state in which the facilities are located.

Sports Palace had many weaknesses, so that the intention of the mayor of Cartagena is requested at the next full permission and commitment from other opposition groups to conduct an external audit, which contrast the original project with the final result.

As found by the Mayor and Deputy Mayor during his visit with the media, the project originally the Palace of Sports does not match the facilities and presents important shortcomings, which disabled to use.

It is for this reason that the mayor of Cartagena want to know why those changes were made, how they did it and also a technical and economic assessment is made.

The mayor also announced that the work of the technicians responsible for this project will investigate.

Besides demand accountability, journalists have asked if there is a correction of the deficiencies in the Sports Palace and Lopez explained that is what we have to say but ask for a report of architectural and sports fitness.

What we do know is that with the debt we owe, we can not keep spending money in Cartagena overcome this sort of thing now.

There are more urgent things to do as attention to districts and councils, to families at risk of exclusion, and so on.

I will not open the gates of the Palacio de Deportes until they not corrected and that will be much more expensive, has continued explaining the mayor.

Jose Lopez, accompanied by the Deputy Mayor, Ana Belen Castejon and the Councillor for Sports, Ricardo Mowing tour with journalists the Sports Palace, showing the most significant shortcomings such as:

-The Absence of electrical connection, which is pending for several months.

- Unable to testing machinery as sewage, air conditioning, boilers, dehumidifiers.

-The Building is not sustainable and has energy deficit.

No radiation plate which implies a high cost of maintenance.

-The Pool isolation zero.

The pool and one of the tracks are separated with a plastic panel so the highly corrosive chlorine vapor expands throughout the grounds of the palace.

-The Parquet used on the tracks is not suitable for the practice of sport.

-The Surveying the floor of the main pavilion is irregular.

-There Water leaks in numerous outbuildings.

-The Cover is danger of detachment of the plates due to incorrect adjustment and use of the material, with numerous deformations expansion.

-The Evacuation plan does not meet the minimum criteria, missing doors and evacuation in different areas.

-The Electrical and communication lines are not suitable for sports broadcasts.

There's a large number of machines and elements of the flag they are oxidized.

-The Light projectors do not have technical gateway.

- There is no type of video surveillance system to ensure the safety of the facility and there is also no basic equipment for the kit and nursing.

- The offices have no furniture, there are only 10% of needs met.

- Problems of accessibility to the building with uneven pavement and puddles widespread, with danger of falling.

-The Foreign ecinto r is undischarged with many deficiencies finishes.

These are some of the defects that the mayor stressed during his visit, and stressed that every effort will open the pavilion but still all being remedied, the pavilion is very difficult to maintain.

A PALACE OF SPORTS OF 21 MILLION

The Palace of Sport was scheduled to be inaugurated in the summer of 2007, but, for the aforementioned problems still will not open to the public.

The Government Commission Consortium Sports Palace Cartagena decided after the result of the scale of the specifications, award to the temporary union of companies Dragados SA and SA Emurtel building this infrastructure amounting to 13.2795 million euros .

The final cost of the work was undertaken by the Autonomous Community as a whole, through its funding.

Finally, the cost of construction of the Palace of Sports amounted to 21 million euros.

Sports Palace has an area of 21,000 square meters and has a specific sports center occupies 10,000 square meters, with a central hall capable of hosting big events, equipped with additional facilities spread over basement, ground floor and first floor, where they will located the offices of the Department of Sports.

The sports center also has a swimming pool and auxiliary pavilion.

Racing Hall has a capacity for 5,000 spectators.

It was also thought that there is a cafeteria on the top floor of the indoor pool, weight rooms, saunas, and whirlpool tubs, sports court with motorized curtains.

MAYOR TRIES TO KEEP ay "N TRAIN IN UBICACIÃ" CURRENT N

When asked by reporters about the issue of station Mandarache, Mayor Jose Lopez has he explained: I have not asked me one, if Cartagena High Speed ​​says that until now was the mayor who decided where to locate, it is my and the commitment of the government team that the station remains in the Avenue Victor Beltrí, because there is no need to move the location of 800 meters.

GETS IN SUSPENSION "N LAND SALE REEL

Following questions from reporters, the mayor explained that it is suspended for the land is dig for more than 20 years we have been saying the same thing already.

The hill is the Palace Pinwheel Hasdrubal.

Roman Forum are in the whole Mediterranean area but not a Carthaginian palace prince.

I is not not want to sell plots but I can not guarantee my economic momentary success killing the future of Cartagena, which is in the archaeological tourism.

Jose Lopez has continued explained that we will try to make the Windlass Hill and even the Monte Sacro excavate.

And if those lands have archaeological remains, you can build.

And if there were archaeological remains, perhaps even the idea could be a museum.

Regarding traffic light cameras, the mayor explained that they have already turned off the cameras and we want to study if we can use them as traffic control, but tax collection effort.

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información