Monday, November 3rd, have begun work on water infrastructure replacement and remodeling Ripoll Captains Avenue, which will involve cutting the two-lane uphill to the Plaza de Bastarreche practically to completion.
This morning we have undertaken the task of perimeter fencing that will act first, as well as horizontal and vertical signaling sections affected by changes in traffic.
The first thing that will be undertaken will be the installation of a new pipeline to supply drinking water, 400 and 450 mm extending below the two carrile rise and his shabby caused numerous faults and subsidence of the road.
The Traffic Bureau of the local police reported that cutting those two lanes Captains Ripoll, let landlocked stretch of Carlos III, located behind the Polytechnic University, who nonetheless remain open to traffic to service the existing buildings and permit parking.
To this were marked along this stretch some areas to allow the passage of two vehicles encountered.
The remodeling project Ripoll Captains Avenue is an action to be performed with a surplus of more than 4 million of the concession of water service in 2012, Hidrogea.
It has a budget of around a million and a half euros and will be executed within a period of five months and a half by local company MGM.
Among the innovations of this project, the removal of the current middle of the street and the extension of the sidewalk located on the side of the houses and stores up to four meters wide is included to facilitate walking and shopping.The councilor area, Francisco Espejo, has indicated that this action comes in response to the demands of neighbors with which it has maintained an open dialogue during processing and have introduced numerous suggestions and contributions, it has where possible technically.
In this sense it has taken into account the concerns of neighbors for the removal of parking. According mirror this reduction will be minimal as it will remain at around 55 (currently there are 60), to suppress the central boulevard, will be located on the curb side where there are no houses, which also go a bici.Otra rail developments will improve the parking of buses currently accumulating in the Plaza Bastarreche, for which they are to have two docks to the top of the avenue, adjacent said plaza.Las works will be completed with the renovation of pipelines and storm water, replacement of sidewalks, new types of lighting with more energy efficient and more green areas, so that are to recover nearly a hundred trees to be placed in beds in the central and lateral area, plus a hedge that will be available in what will be the medium to prevent pedestrians crossing outside the places enabled ello.Según the mayor of Planning and Infrastructure, with performances that will take place at Captains Ripoll, which is being done in Sebastian Feringa and already finished projects and works in Avenida America and the streets of downtown, was practically impossible circle of investment in the town, pending the Plaza del Lago, where the archaeological remains have been found, it has been necessary to modify the project.
OTHER PROJECTS FORWARD Hydra ULICOS
While still below the other two major renovation projects hydraulic with infrastructures, such as those that are undertaken at Alfonso XIII of Sorrows, whose performance is circuscribe at this time to the roundabout entrance to the cella Conesa Quarter and Calderon;
and that is realized in Ussel Guimbarda Street next to Park Juncos and most trarde affect Calle Alfonso X the Wise.
Source: Ayuntamiento de Cartagena