The Governing Council has authorized the Murciano Health Service to tender the first phase of construction of the new Health Center of San Anton in Cartagena, amounting to 549,988 euros.
The Murciano Health Service has provided the construction phases of a new health center in the district of Cartagena, which will replace the current to suit the care needs of their basic health area, which has allocated 17,091 individual health cards, of which 3,040 are of Pediatrics.
The construction will take place on a site located in the vicinity of the current health center, in the same Recoletos street of San Antón.
The overall project is divided into phases, and construction will start by block to house the area of ​​Pediatric Care.
In this phase, the construction period is seven months, seven consultations of Pediatrics, both medical and nursing and related public areas and waiting rooms are enabled.
Thus, it will be released on these services occupy space in the current building of the health center, which will be made available to other services.
Source: CARM