The general contractor for the paving of the streets of Canyon, Prince of Vergara and Air has started work today stamped concrete repair the road, which had numerous chipped due to the haste with which the work was completed before Week Easter.
The rainfall days before s of completion and have not waited long enough for drying caused it to lift the protective layer of resin with which it was treated.
As reported by the Department of Technical Infrastructure and Services the cost of this repair, which depended final acceptance shall be borne by the contractor, without a surcharge for the council.
The same sources explained that it has waited for the arrival of warm weather to proceed with the repair and its duration depend on it will not rain.
In principle two phases are planned: one of about ten days, until the end of next week, which will act on the streets of Canyon and Principe de Vergara, and another phase, roughly similar to Air Street.
The works consist of the complete removal of defective resin layers by sanding and stripping, and application of new hands with dark dye, respecting the drying time between them.
Also wait long enough to re-open to traffic.
Source: Ayuntamiento de Cartagena