The road will be a new avenue Torreciega summer (28/11/2012)

Today have started the renovation work of sanitation and urbanization Didio Tito Avenue, whose execution time will last eight months and join the action already initiated in the hull of the city and in the vicinity of Juan Carlos I

One of the key works projected by the Department of Infrastructure and the concessionaire from the municipal water supply, Aquagest Murcia is the remodeling of Titus Avenue at Torreciega Didio, which started today will rush renewal drinking water and sanitation as well as the urbanization of the street.

With regard to the first, was introduced 546 meters of potable water pipe ductile iron, 376 meters of PVC sanitation pipe special pipe 160 meters of reinforced concrete storm.

The urbanization of the environment, will be a very palpable change in appearance in the strip, which will include 392 meters linear of bike lanes, sidewalks, cobblestone pavement, 300 square meters of gardens and 125 square feet of play area for children .

The scheduled execution time for this performance is eight months, so that the new venue would be ready for summer.

The work the company is doing EALSA.

OTHER STREETS IN WORKS

For the rest of that infrastructure is coordinating work in the city, the most advanced are the hull, specifically San Francisco street, which will end in a month. Following the start of the Duke and San Antonio streets the poor, be addressed, probably in parallel.

The other axis of performances in the center of the street is the Arch of Charity, which this week will finish paving work to proceed, since the beginning of December, to place the stamped concrete, which take two to three weeks .

Then in mid December will start work on the Calle San Vicente.

Finally, the proposed redevelopment of the Avenida Juan Carlos I, continues to focus on the street Sighs, where collectors are bringing rain and, once completed the work on that street, and in January, will begin in the proper avenue that, where in addition to improving water collection infrastructure, urbanized street also upgrade and modernize its appearance, with a landscaped median and bike lanes.

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información