Next summer could be ready the underground car park on Avenida de America, given the pace of work that is being developed, as reported from the Department of Planning.
Have already been placed on 30% of the foundation slab of the pillars, a task that is framed within the first phase of works.
And, as of August 27 will start pouring concrete sections of the floor of what would be the street.
In August, the rate will drop slightly, namely from 13 to 26, for rest of staff.
The park will have about 350 seats, will be built on one level, ranging from Mexico to the square of Bastarreche, and will involve the rearrangement of the surface with the removal of the existing trees and relocation of the center four lanes Avenue.
In addition, sidewalks will have side 14 meters wide.
The construction and management of parking in the Avenue of the Americas was awarded by the City to González Soto for a fee of 215,730 euros.
Source: Ayuntamiento de Cartagena