Work continues at the Palace of Sports (08/09/2011)

Work on the Palacio de Deportes continuing. Slowly but surely, the main town sports infrastructure will cover compliance phases.

The work focuses currently on the completion of the cover and interior installation.

On the cover is undertaken at this time placing the penultimate layer of waterproofing, black color, which already has a 40 per cent of the total area.

As you may recall the cover consists of several layers as a function that will insulate the interior from inclement weather.

First put a motherboard, which was followed by a black film that will prevent moisture and condensation.

Plates were then placed on top of thermal insulation, followed by a waterproofing sheets also black, which are being installed now.

The work completed by placing a sheet of aluminum silver color that will give you the unique aspect in the draft.

The councilman of Deportes, José Cabezas, who usually keeps track of the works, said that these tasks are slow because of the way the cover that prevents the placement of scaffolding and requires the use of forklifts to safely access the work areas.

Regarding the interior, the works also advanced.

They're almost finished changing rooms, toilets and other depedencias and working on the tiling of the pools whose vases are covered with tile.

What will be the last to put chairs and the floor of the tracks, which will be removable to host celebration of performances and concerts.

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información