The placement of the pieces that make up the arch of the bridge district of Concepcion is in its final stage and, between Wednesday and Thursday morning, workers are taking charge of the welding of the parts, work will be reviewed on Friday to proceed to remove the towers have served as support for this action.
In this way, and from late Friday, traffic has resumed on the bridge, after the court opened on Monday and has affected the passage of vehicles between 9.30 and 20.00 hours.
After removal of towers and the tables that hold the bow, come Monday the placement of the hangers that hang of it and get hooked to the board.
With the installation of the arc is terminated construction of the structure, and you just need the assembly floor, railings and lighting, is scheduled to complete the work is finished in October.