Both projects, which holds the City Council through Aquagest, involving the renewal of water infrastructure, performance that is nearly finished, and remodeling on the surface, it begins to be undertaken now
The pace of renovation work on water infrastructure and urban services that the City is currently carrying out on the streets Juan Fernández and Ramón y Cajal, through the concessionaire of the water service, Aquagest Murcia, does provide that within about three months will be completed.
The project is running since early December in the last section of the street Juan Fernandez, who covers the two blocks between Trafalgar Street and Jorge Juan, and is completing the renovation work in depth of water and sewerage networks and will begin work on the surface to lower the roadway, paving and lighting position.
As for the action in Calle Ramón y Cajal, which began in October, is in the same situation with the detailed work completed, being to make the surface treatment includes the replacement of sidewalks, which have 5 meters wide with a bike lane and a half feet, and paving and lighting renewal and trees.
This project is large, involved the replacement of the wastewater network, with the installation of two collectors and the renewal of all rush home and sinks.
In this first phase, which runs from the rotunda of the English Court to Doctor Barraquer and will finish in about three months, is followed by a second phase, two blocks to The barriers, which will invest another three months, as minimum.
Source: Ayuntamiento de Cartagena