The councilman of Social Care, Antonio Calderon, yesterday visited the works of the Day Center of Los Dolores, accompanied by the director of the Municipal Institute of Social Services, Antonio Mule, Senior program manager and the staff running this show.
Construction is scheduled to end in October, creating a greater day center with capacity for 30 seats, according to the law in this matter and based on availability square meters for each user.
Have everything you need to address social health and therapeutic needs of dependent persons entering the center.
The building structure of more than 600 square meters and has total closure and completion of various facilities, and in the coming days, carpentry work and other works concerning the end of the building as the project that began last summer to come into operation on the end of this year.
The City of Cartagena offers this service as a real alternative to expensive residential accommodation to ease the burden of dependency for the family unit.
The budget execution of the project amounts to 413,567 euros, financed by the Ministry of Social Policy, Women and Migration in the Autonomous Community of Murcia and the city of Cartagena.
Source: Ayuntamiento de Cartagena