Works of adaptation of the university district begin their journey (07/06/2017)

The mayor, José López, visited this morning the adaptation works that are carried out in the PERI CA4, in the so-called University District, to learn firsthand the deficiencies that exist in the streets of this area as a consequence of the use of Inadequate materials or by the poor finish of the original works, and that are being arranged.

The company awarded these adaptation works and municipal technicians have found "what the neighbors are suffering almost from the first day: streets that have sunk because cobblestones were laid on gravel, instead of putting concrete and compacting well the fringe Of gravel;

The buildings do not have asphalt cloth and when the streets sink there are damp in the buildings themselves, slab slabs of a centimeter have been used in the streets that have been broken that now is going to be replaced ... and in the end they will try to rectify all The pegas that this work has "explained the mayor.

Specifically, the municipal infrastructure technician, Angel Alcaraz, explained that the main job will be the resurfacing of the streets, which mixes the traffic with the pedestrians, and now there are many seats in the Paved.

This problem exists especially in housing encounters which in many cases provokes water leaks in the interiors of the basements of buildings.

Some areas that were simply paved with concrete will also cobble.

Likewise the use in the original work of materials that are not working as intended, have been detected that will be replaced by more resistant materials.

In concrete in the zones of ladder will replace the slab slabs of a centimeter that were placed, and that in many cases have been broken, by stone slabs of the cabezo of two centimeters.

The stone to be used is the one used in the rest of the historic center, to homogenize the pavement.

In addition, as regards the structures made to display archaeological sites on the boulevard José Hierro, it has been detected that interior materials, uncoated timbers and interior mortar were used in the structures surrounding it, so that part of the deposit goes To have to rectify it because it is deteriorating progressively.

The mayor also indicated that there is a piece of garden in a rocky area that has not been able to be integrated into the project of adaptation, since at the time it was not charged to the expense account of the awarded company and paid with Municipal money.

The legal services of the city council will study why 50,000 euros of public money were used instead of executing the guarantee of the promoter company, and, if considered appropriate, will be made available to the Prosecutor and the Courts.

The work will be carried out under the project's execution, which amounts to around 600,000 euros, and is expected to be developed over the next three months, although this could be delayed due to some work in coordination with A private work in the area.

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información