The mayor of Cartagena, Jose López, reported Monday morning that the Sports Palace already has electricity, which has light and therefore some of its spaces can already be used.
However, he recalled that problems remain on the central court with the flatness of the ground and the parquet.
As explained by the mayor, there are still finishing things and waiting for the reports of the technicians, who are doing a thorough work so that the company delivers, if not 100%, at least the highest percentage of the finished work.
The parquet of the large, floating and detachable track is what most concerns the City Council, since it is not desired to cause an injury in high-performance athletes because they have a firm deficient.
Lopez has explained that his determination is to continue to claim the company while the technicians so dictate.
However, he stressed that as soon as you can not exhaust more tracks you will see if a new one is placed.
It should be remembered that the contradictions continue between the Institute of Biomechanics of Valencia - which has ruled that the ground is not suitable for the practice of sports and has certified that the spherical boot badly - and the construction company.
During a visit to the press, the mayor has shown to the journalists some of the deficiencies that the building presents, and that it is necessary to solve as soon as possible in order that it may be usable, as they are Of the central track, maintenance of lighting lamps in this same space, lack of finishing in the plastering of some walls or finishing errors in the skirting board some showers, among others.
On the other hand, we are already working on the efforts to provide this space for air conditioning.
Source: Ayuntamiento de Cartagena