The City of Cartagena is currently processing seven projects to install photovoltaic solar plants in the municipality, with an investment of approximately 11 million euros that will allow us to have a production of about 17 megawatts, which would be equivalent to giving service to about 8,000 homes.
In recent months, the Consistory is receiving many license applications regarding the installation of new photovoltaic plants, so that the mayor of Cartagena, Ana Belén Castejón, as responsible for Urban Planning which is the area from which the licensing processes are processed activity, has given the appropriate instructions to the technicians so that these types of projects are expedited as much as possible, "since the production of clean energy can and should be an identity sign of the municipality of Cartagena."
In any case, the power to grant this type of activity licenses, classified as 'exceptional use', is the General Directorate of Territorial Planning of the Autonomous Community.
In fact, the Government team is determined to introduce sustainability criteria in all its actions in Cartagena.
"For this municipal Government, the fulfillment of the objectives of the 2030 Agenda is a priority and this is reflected in the programmatic agreement that we present at the beginning of this term," Castejón said.
The mayor also stressed that the legislation that the Government of Spain is promoting to promote this type of clean energy "is being an incentive for local businesses."
PHOTOVOLTAIC PLANTS IN PROCESSING IN THE MUNICIPALITY
PLEX 2017/13
'GUĂŤA' PHOTOVOLTAIC SOLAR PLANT
Los Angeles Area, Polygon 11, Plot 241 (Within the Cartagena Speed ​​Circuit)
Developer: FV PLAN GUĂŤA CARTAGENA, SLU
Installation area: 70,000 m2
Budget: 156,428, € 92
Power: 5,644,600 kW.
Processing status: A report was sent by the City Council on November 29, 2018. It is pending resolution by the General Directorate of Land Management.
PLEX 2019/1
SOLAR PHOTOVOLTAIC CENTER
Place of the Porch, Vista Alegre
Developer: ELVIA RENOVABLES, SL
Surface: 11,428 m2.
Budget: € 1,075,427.98
Power: 2,000kw
Processing status: The City Council sent the required documentation to the owner on September 6, 2019 and is pending resolution by the General Directorate of Land Management.
PLEX 2019/11
“CARTAGO I” PHOTOVOLTAIC SOLAR PLANT
Finca Casa Blanca, Plot 162, Polygon 60
Developer: CARTAGO SOLARBAY, SL
Surface: 14.972 m2.
Budget: € 1,328,138.53
Power: 2 mw
Processing status: The City Council has required the repair repair owner.
PLEX 2019/12
“CARTAGO II” PHOTOVOLTAIC SOLAR PLANT
Finca "Los Sánchez 3" Plot 33, Polygon 13, (Marfagones Mills)
Developer: CARTAGO SOLARBAY, SL
Area: 14,988 m2
Budget: € 1,138,379.20
Power: 2 mw
Processing status: It is currently in public information within the procedure being carried out by the City Council.
PLEX 2019/13
SOLAR PHOTOVOLTAIC PLANT
Place Los Pinos.
Polygon 59, plots 214, 215,225,226,420,421
Promoter: GEMBER INVERSIONES, SL
Area: 20,000 m2
Budget:
Power: 950 kW
Processing status: Pending report of the municipal technical services.
On November 8, 2019, the City Council requested information from the interested party.
PLEX 2019/15
PHOTOVOLTAIC SOLAR PLANT FV CAMPOS DE CARTAGENA
The Village, Altitudes, plots 41,42,57,153,155,162 and 231, Polygon 19
Developer: AMBER SOLAR POWER CINCO, SL
Area: 144,478.50 m2
Budget: 4,243,903, € 35
Power: 8.17 mw.
Processing status: Pending report of the municipal technical services.
On November 28, 2019, the City Council requested information from the interested party.
PLEX 2019/16
“FV LA ASOMADA” PHOTOVOLTAIC SOLAR INSTALLATION
Polygon 136, Plots 92, 152 and 263. Derribao Mill.
Developer: LUMINORA SOLAR CUATRO, SL
Surface: 86.480m2
Budget: € 2,647,854.25
Power: 4.49 mw.
Processing status: Pending to be informed by the municipal technical services.
The license application entered on October 18, 2019.
Source: Ayuntamiento de Cartagena